As a beverage product processing facility, this project involved extensive process piping coordination, which was facilitated by a Digital Plan Room. Our team worked in close coordination with the architect and owner to design and install many complex systems and finishes, including: a Class 1 | Division 1 certified compounding laboratory, a fully-equipped laboratory ventilation system, a process waste delivery system, adding efficiencies to the pH equivalization and effluent handling system, and installation of the 4 Million BTU Falling Film Evaporator Tower.
Since this was an active industrial plant, careful coordination and planning was required. The Compounding Lab was constructed right next to an existing high-speed bottling line with volumes of up to 200,000 gallons per day. During construction, we ensured that the site was secured when workers were in the plant by building temporary barriers and working around the factory schedule. Since the plant manufactures food products, our team also conformed to Good Manufacturing Policies (GMP) catered to food and beverage manufacturing and safety.