Pricing to Beat Initial Budget
Carroll Daniel provided a concept budget for the station replacement several years before construction started. When the city was ready to begin, our preconstruction team worked aggressively on pricing exercises, reaching a number that was lower than the original budget without sacrificing design. Savings attained during preconstruction and throughout the project enabled the city to add additional access control measures and safety cameras.
Achieving Schedule Despite Weather & Site Delays
The greatest challenge for Station No. 2 was a combined two months of wet weather and the position of the site. The site was located adjacent to a state botanical garden and a heavily trafficked bridge that was undergoing construction. The team carried out erosion control and protection measures to safeguard the nearby state botanical garden and neighbors’ property and coordinated with the bridge contractor to be sure material deliveries were not hindered by the bridge construction. In an additional effort to maintain schedule, Carroll Daniel coordinated with officials for midnight concrete pours to avoid rainfall and expedite the project. Our resilient team finished the project early with zero lost time due to accidents.
Ultimate Design & Amenities
Built on a different site than its 1954 predecessor, the new 14,000 SF Station No. 2 includes the latest fire/rescue support amenities:
- Theater-style dayroom/classroom
- Commercial kitchen
- Fitness room
- Private restroom/shower units
- Administrative and triage space
- Turnout gear storage
- Cleaning facilities
- Decontamination suite